Showing posts with label Bridge Users. Show all posts
Showing posts with label Bridge Users. Show all posts

Wednesday, July 28, 2010

County vehicle fee will fund new Sellwood Bridge

One of the most difficult parts of any large transportation project is finding funds. A new Multnomah County vehicle registration fee that goes into effect in September will help fund the Sellwood Bridge replacement. It was adopted in 2009 by the Board of County Commissioners. The fee is $19 per year per vehicle, or $38 for a two-year renewal.

Multnomah County residents will pay the new fee to the state DMV when they renew their state vehicle registration. If you do not have an address change at the time of renewal, you can pay the new fee at a DEQ vehicle inspection station after passing the required emissions test.

The fee goes into effect for vehicles in Multnomah County with registration expiring during September 2010 or after. Please note that it’s not possible to avoid the fee by renewing early. The fee is based on when a vehicle’s registration expires, which can’t be changed. Revenue from the fee will be used to replace the Sellwood Bridge, as required by state law.

The fee will be in effect for approximately 20 years, to pay off construction bonds for the new bridge. The fee is projected to raise $127 million to help pay for the new bridge. Clackamas County is expected to adopt a vehicle fee dedicated to the Sellwood Bridge project later this year.

For information on Multnomah County’s vehicle fee, visit www.multco.us/vrf, email multcovrf@co.multnomah.or.us, or call 503-988-4296.

Thursday, July 22, 2010

What type of new bridge would you like to see?

Many thanks to the 113 people who joined us last night for our open house at Oaks Park. Nearly everyone who attended submitted a comment form with their thoughts about the six bridge types under consideration to replace the Sellwood Bridge. Our project team enjoyed talking with folks and learning more about what people like and don’t like about the options.

If you weren’t able to attend the meeting, there is still time to make your voice heard in the bridge type decision. Just take the online survey located on the homepage. You can do so through Sunday, August 8. The results of the survey will be compiled and provided to the Community Advisory Committee before they make their bridge type recommendation to decision makers. The decision should be announced this fall. Keep checking the project website for updates.

Thanks as always for your interest in the project.

Wednesday, May 12, 2010

Sellwood Bridge video wins national award

A video tour of the Sellwood Bridge narrated by former Multnomah County Chair Ted Wheeler received a national Best of Class award for being the top video produced by a county in 2009. The award was announced by the National Association of County Information Officers.

In the short video, Chair Wheeler takes a tour of the bridge, pointing out its problems and the issues involved in deciding its future. The video has had nearly three thousand views. Using visuals of the bridge to explain the project helped to educate the public and build consensus that it was time to deal with the failing structure.

Thursday, December 17, 2009

Keeping a bridge open during construction

A frequent question we’re asked is “Will the Sellwood Bridge stay open during construction?” The short answer is yes. The new bridge will be built in stages so that a river crossing remains available to traffic at most times during construction. This plan responds to a common public concern heard during the planning phase.

During planning many businesses told us their health and survival depended on the Sellwood Bridge remaining open during construction. Many business owners said they would lose customers during construction, due to the lack of nearby alternate river crossings if the Sellwood Bridge were closed. Nearby neighborhoods and traffic planners also warned of problems that would arise if the 30,000 vehicles that cross the bridge each day needed to detour to other congested bridges during construction.

These concerns led local jurisdictions to choose a preferred alternative that keeps a Sellwood Bridge open during several years of construction. Here’s how it works:

• In the first stage the first half of the new bridge is constructed along the south side of the existing bridge. Traffic continues to use the old bridge. At the end of this stage, traffic is shifted from the old bridge to the completed half of the new bridge, which will be about 33-feet wide. Current plans call for this narrow structure to have room for two 12-foot traffic lanes and one 8-foot sidewalk for bikes and pedestrians, but no shoulders or bike lanes. The old bridge is then removed.



• In the second stage, the second half of the new bridge is built where the old bridge used to stand. Traffic continues to use the completed half of the new bridge. By the end of this stage the two new halves of the bridge are connected, like two sides of a zipper.



The deck of the completed bridge will be 64 feet wide, with:
• Two 12-foot traffic lanes
• Two 6.5-foot shoulders/bike lanes
• Two 12-foot sidewalks

There will be brief periods during construction when the contractor will need to close the bridge to traffic. These include when lane markings are placed and when connections are completed between the bridge and SE Tacoma Street and Highway 43. The County will work with the contractor to limit bridge closures as much as possible. Bridge closures could be scheduled on weekends or evenings to minimize the impact on bridge users.

Keeping the Sellwood Bridge open is important to many local businesses and bridge users. Our plan should keep traffic flowing across the bridge as much as possible during construction.